Walking a bill of materials down every level to find the total quantity of each component needed.
To make 100 finished units, MRP multiplies quantities down the tree: 100 finished units need 200 sub-assemblies, which need 800 brackets, and so on. Phantom assemblies are passed through, effectivity dates decide which version applies, and scrap factors add to the quantity.
The explosion is where volume comes from: a few thousand finished products can explode into millions of component requirements.